Question NW141 to the Minister of Water and Sanitation

Share this page:

10 March 2022 - NW141

Profile picture: Horn, Mr W

Horn, Mr W to ask the Minister of Water and Sanitation

On what date (a) will construction of the water pipeline from the Xhariep Dam to the Mangaung Metropolitan Municipality commence and (b) is the construction envisaged to be completed?

Reply:

a)  Construction of the water pipeline from Xhariep Dam to Mangaung Metropolitan Municipality is scheduled to start in July 2025. The next phase of the project will comprise of detailed designs, securing funding and contracting agreements.

b) It is envisaged that the project will be completed by June 2029.