Question NW1267 to the Minister of Cooperative Governance and Traditional Affairs

Share this page:

25 June 2021 - NW1267

Profile picture: Gumbi, Mr HS

Gumbi, Mr HS to ask the Minister of Cooperative Governance and Traditional Affairs

What is the total (a) number of water tankers that operated in the Inanda area since 2010 and (b) amount spent on (i) water tankers and (ii) bulk infrastructure in the specified area in each specified year?

Reply:

1267

Financial year

Description

Project No.

YTD Actuals (at 30 April 2021)

Total per FY in Rm

2020-21

INANDA NEWTOWN C SEWER RETICUL

Y8136D

                   0.818

 

 

INANDA B-SINAMUVA DRIVE SEWER

Y8783D

                   0.228

 

 

 

 

                   1.046

      1.046

2019-20

Umbhayi Housing Development

X8224

                   0.152

 

 

INANDA NEWTON C SEWER RETICULATION

Y8136B

                   5.630

 

 

INANDA NEWTOWN C SEWER RETICUL

Y8136C

                          -  

 

 

INANDA NEWTOWN C SEWER RETICUL

Y8136C

                          -  

 

 

 

 

                   5.782

      5.782

2018-19

INANDA NEWTON C SEWER RETICULATION

Y8136B

                   0.186

 

 

Inanda B Sinamuva drive sewer

Y8783

                   0.268

 

 

 

 

                   0.454

      0.454

2017-18

Inanda Newtown 'C' Sewer Reticulation

Y8136B

                   0.138

 

 

 

 

                   0.138

      0.138

2016-17

 

 

                          -  

 

 

 

 

 

0

2015-16

 

 

0

 

 

 

 

 

0

2014-15

 

 

0

 

 

 

 

 

0

2013-14

Inanda Glebe Sewer Reticulation

Y6459

                   0.079

 

 

 

 

                   0.079

      0.079

2012-13

Etafuleni phrase1 and 2 collector

Y6523

                   2.871

 

 

 

 

                   2.871

      2.871

 

 

 

 

 

Grand total

 

 

 

10.3698

BACKGROUND INFORMATION:

It is to be noted that parliamentary question require information since 2010, however information submitted by the Ethekwini Metro is for period since 2012/13 financial year. According to the Metro, information before 2012/13 is not readily available and therefore will require more time to be extracted and submitted.

Source file