Question NW1143 to the Minister of Cooperative Governance and Traditional Affairs
25 June 2021 - NW1143
Gumbi, Mr HS to ask the Minister of Cooperative Governance and Traditional Affairs
What (a) is the total amount that has been spent on (i) water tankers and (ii) bulk water infrastructure in Ward 3, uMzinyathi, in the eThekwini Metropolitan Municipality in each financial year since 2010?
Reply:
1143
Financial year |
Description |
Project No. |
YTD Actuals (at 30 April 2021) |
Total per FY in Rm |
2020/21 |
MZINYATHI |
X7533 |
- |
|
|
ETAFULENI TOWNSHIP |
X5653D |
0.185 |
|
|
|
|
0.185 |
|
2019/20 |
Intathakusa ET & Outlet pipeline |
X5028B |
2.706 |
|
|
MZINYATHI,EMAQADINI RETICULATION |
X7533 |
8.774 |
|
|
Umzinyathi - 16 Water tankers |
32.120 |
|
|
|
|
|
43.600 |
|
2018/19 |
Intathakusa ET & Outlet pipeline |
X5028B |
9.997 |
|
|
Etafuleni Township |
X5653 |
0.111 |
|
|
Intathakusa elevated tower & outlet pipeline |
X5028A |
3.746 |
|
Umzinyathi - 15 Water tankers |
27.375 |
|||
|
|
|
41.229 |
|
2017/18 |
Intathakusa ET & Outlet pipeline |
X5028B |
0.011 |
|
|
Mzinyathi infill project |
X6540 |
0.001 |
|
|
Intuthuko infills |
X4506A |
- |
|
|
Umzinyathi - 12 Water tankers |
19.710 |
|
|
|
|
19.722 |
||
2016/17 |
|
|
|
|
|
Intathakusa ET & Outlet pipeline |
X5028B |
0.066 |
|
|
Etafuleni Township |
X5653B |
0.737 |
|
|
Umzinyathi - 10 Water tankers |
14.600 |
|
|
|
|
|
15.403 |
|
2015/16 |
|
|
|
|
|
INTHUTHUKO WATER INFILLS |
0.003 |
|
|
|
Intathakusa Project |
- |
|
|
|
Umzinyathi - 10 Water tankers |
12.775 |
|
|
|
|
|
12.778 |
|
2014/15 |
Ekukhanyeni/Mzinyathi |
X3675 |
0.011 |
|
|
Intuthuko Water |
X4506 |
0.180 |
|
|
Mzinyathi Baseline Survey |
X5720 |
0.570 |
|
|
|
|
|
0.761 |
BACKGROUND INFORMATION:
It is to be noted that parliamentary question require information since 2010, however information submitted by the Ethekwini Metro is for period since 2011/12 financial year. According to the Metro, information before 2011/12 is not readily available and therefore will require more time to be extracted and submitted