Question NW922 to the Minister of Public Enterprises
05 May 2021 - NW922
Van Minnen, Ms BM to ask the Minister of Public Enterprises
How does he intend to recoup wasted and fruitless expenditure running into millions of Rands from the failed accommodation block that was constructed for workers at the Kusile Power Station?
Reply:
According to the information received from Eskom
Eskom is in the process of quantifying the losses incurred and the parties against whom legal actions should be taken. Counsel has been engaged to advise on the merits of intended action.