Question NW2827 to the Minister of Health

Share this page:

17 December 2020 - NW2827

Profile picture: Chabangu, Mr M

Chabangu, Mr M to ask the Minister of Health

(a) On what date will the project commence to refurbish the wards at Dr George Mukhari Academic Hospital in Ga-Rankuwa and (b) what amount is budgeted for the project?

Reply:

According to the Gauteng Provincial Department of Health,

a) The project of refurbishing the eight (8) wards as, indicated in the response to Question 2743 by Ms N Chirwa was successfully completed and the wards are fully operational. Below are the dates of occupation achieved for each of the wards:

 

Ward 1: 13 July 2020

Ward 2: 08 July 2020

Ward 3: 31 July 2020

Ward 4: 28 August 2020

Ward 5: 13 July 2020

Ward 6: 08 July 2020

Ward 7: 28 August 2020

Ward 8: 28 August 2020

b) The refurbishment project was done at a cost of R186,000,000.

END.