Question NW1977 to the Minister of Human Settlements, Water and Sanitation

Share this page:

19 October 2020 - NW1977

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Human Settlements, Water and Sanitation

Given that the community of Motala Farm in Ward 15 in the Ethekwini region has been without houses and proper sanitation since the dawn of democracy and that even though land was identified on which to build them houses, nothing has been done, by what date does she envisage will her department build proper houses and provide sanitation to the specified community?

Reply:

Based on the information provided by the Kwa-Zulu Natal Provincial Department of Human Settlements, the project is at a pre-feasibility stage. An application was received by the Provincial Department of Human Settlements from eThekwini Metropolitan Municipality, which was duly processed and feedback was accordingly provided to the Metropolitan Municipality. The eThekwini Metro is currently incorporating all the comments received from the Provincial Department of Human Settlements, to ensure that the project meets the funding criteria for the Human Settlement Development Grant (HSDG).

The table below provides the timeframes and envisaged dates for the execution of project tasks which includes the construction of houses.

Activity

Time Frame

Approval of project implementation funding

February 2021

Detailed planning studies

October 2019 - June 2021

Pre – Implementation Submission Consultations

April 2021

Final planning application submission

May 2021

Planning approval

June 2021

Submission and approval of Tranche 2 application to Provincial Department

July – September 2021

Installation of Services

October 2021 - March 2022

Top structure construction

April 2022