Question NW1320 to the Minister of Agriculture, Land Reform and Rural Development

Share this page:

22 July 2020 - NW1320

Profile picture: Steyn, Ms A

Steyn, Ms A to ask the Minister of Agriculture, Land Reform and Rural Development

Whether the Minister of Finance approved the construction of a new public-private partnership office block for her department; if so, (a) what is the projected cost and (b) by what date will construction start; (2) whether, considering the merger of the two departments, there is still a need for the new office block; if so, what are the relevant details? NW1688E

Reply:

1. The Department registered two separate projects with National Treasury prior to the merger of the former Department of Rural Development and Land Reform and the Department Agriculture, Forestry and Fisheries. The Minister of Finance has approved the construction of a new public-private partnership office block project registered by the former Department of Rural Development and Land Reform. The other project is still at the appointment of Transaction Advisory Team to undertake a Feasibility Study on the project. All follow-up questions will be applicable to the project by the former Department of Rural Development and Land Reform.

(a) Please refer to the table below.

Item

Amount

Project Cost

R2.1 Billion

Private Party Contribution

R1.43 Billion

Government Contribution

R 0.67 Billion

(b) The projected construction start date is October 2020.

(2) There is still a need for the continuation of the project due to office space challenges and maintenance issues in the current buildings occupied by the Department. The Department also considered the expenditure already incurred on the project, termination of the project would have resulted in wasteful expenditure and legal costs/litigation from the appointed service provider.