Question NW646 to the Minister of Human Settlements, Water and Sanitation

Share this page:

29 May 2020 - NW646

Profile picture: Lees, Mr RA

Lees, Mr RA to ask the Minister of Human Settlements, Water and Sanitation

With reference to her reply to question 34 on 13 March 2020, what are the details of (a) each of the estimated expenses that make up the preliminary cost estimate of R1 941 894 392,00, (b) the payments made by all government and municipal departments and entities to persons and/or consultants on the project since it was initiated up to 29 February 2020, and (c) work done on the project by all consultants since the project was initiated up to 29 February 2020 including but not exclusively by each consultant in terms of (i) name, (ii) profession, (iii) work done, (iv) the amounts paid to each and (v) the dates that the work done by each consultant was completed?

Reply:

The estimated cost of R1 941 894 392 provided in my reply to question 34 was for the entire Driefontein Bulk Water Supply Scheme. The project in question (i.e. Ladysmith (Spioenkop) Bulk Water Supply Scheme) constitutes a third phase of the project. The breakdown is as follows:

 

Driefontein Bulk Complex – Phase 1

Driefontein (Hobsland-Indaka) Bulk Water Scheme

– Phase 2

Spioenkop-Ladysmith Bulk Water Supply Scheme

– Phase 3

Total Cost

MIG Funding

3,023,354

20,042,456

40,699,215

63,765,025

RBIG Funding

116,739,394

281,002,717

479,397,225

877,139,336

Other Funding

   

1,000,990,031

1,000,990,031

Total

119,762,748

301,045,173

1,521,086,471

1,941,894,392

No payments have been made on the Spioenkop-Ladysmith Bulk Water Supply Scheme because the project is still in the feasibility study phase which Umgeni Water undertook to fund from its own coffers.