Question NW1382 to the Minister of Transport

Share this page:

11 December 2019 - NW1382

Profile picture: Mey, Mr P

Mey, Mr P to ask the Minister of Transport

Whether the SA National Roads Agency Ltd (Sanral), will contract with the Eastern Cape Government to work and complete the R62 road up to the border between the Eastern Cape and the Western Cape; if not, what is the position in this regard; if so, by what date will Sanral be contracted to commence the work?

Reply:

The section of the R62 in question from Western Cape border at Haarlem up to intersection with the N2 is declared National Road under jurisdiction of SANRAL. The funding for maintenance of this road is thus prioritised from the SANRAL non-toll budget allocations received from National Treasury.

Based on the SANRAL non-toll funding prioritisation, this section of R62 is in a fair condition with narrow shoulders and currently under full routine road maintenance for daily maintenance. In addition, the special maintenance of 33 km section between Kareedow and N2 I/C was completed in 2018. On the remaining section which is 85 km long the following projects have been prioritised by SANRAL:

a) 20 km of Reseal, and the plan is to:

  1. Advertise for construction in November 2020
  2. Award Tender by April 2021
  3. Hand Over Site to Contractor by May 2021

b) 65 km of Strengthening and/or Improvement, and the plan is to split this into two phases of 30km and another of 35km. The first phase will be implemented as follows:

  1. Advertise for construction in October 2021
  2. Award Tender by April 2022
  3. Hand Over Site by June 2022, and the second phase as soon as the first phase is completed.

 