Question NW1055 to the Minister of Justice and Correctional Services

Share this page:

22 November 2019 - NW1055

Profile picture: Selfe, Mr J

Selfe, Mr J to ask the Minister of Justice and Correctional Services

Whether he has found that all correctional centres conform to the requirements prescribed in terms of section 7(1) of the Correctional Services Act, Act 111 of 1998; if not, (a) why not, (b) which correctional centres have been found not to conform to the prescribed requirements and (c) what steps is his department taking to ensure conformity with the prescribed requirements in all correctional centres?

Reply:

1. Not all the correctional centres conform to the requirements of Clause 7(1) of the Correctional Services Act 111 of 1998 which stipulates the following:

7 Accommodation (1) Prisoners must be held in cells which meet the requirements prescribed by regulation in respect of floor space, cubic capacity, lighting, ventilation, sanitary installations and general health conditions. These requirements must be adequate for detention under conditions of human dignity.”)

(a) The reasons for the non-conformity are:-

(ii) The Department’s correctional centres are made up of a range of facilities built over an extended period of time and they cater for a variety of different purposes to suit the thinking that was prevalent at the time of their construction. Many of centres were not designed to fulfil the objective of inmate detention under conditions of human dignity as is prevalent in the current correctional system;

(iii) Overcrowding in correctional centres which causes accelerated dilapidation of facilities, faster than new facilities can be constructed or the existing ones repaired;

(iv) Backlog of maintenance due to financial and human capacity constraints within both the implementing agent department (DPWI) as well DCS.

(b) There are fifteen (15) correctional centres that do not conform to the requirements (marked by * in the table below).

(c) The department is instituting corrective actions by upgrading existing correctional centres where funds permit, as well as planning the construction of new correctional centres as follows:-

 

Correctional centre

Status

Corrective action

1

Glencoe*

Completed 2019/20

Upgrading contract for a section of the centre was completed in June 2019; Contract 2 is in planning for the remainder of the centre

2

Tzaneen*

Under construction

Construction of a new 500 bed correctional centre to replace zinc structure is underway, due for completion during 2019/2020

3

Lichtenburg*

Planning

Planning for an upgrading project to create additional 234 bed spaces and replace zinc structure is at an advanced stage; construction to commence in 2020/2021

4

Leeuwkop*

Planning

Planning for a new correctional centre to create 1,000 bed spaces and replace zinc structure is at site clearance stage

5

Voorberg*

Planning

Planning for a new correctional centre to create 1,500 bed spaces and replace zinc structure is at site clearance stage

6

Zeerust*

Planning

Planning for a new correctional centre to create 500 bed spaces and replace zinc structure is at site clearance stage

7

Makhado*

Zinc construction

Planning will commence when funds are available

8

Atteridgeville*

Zinc construction

Planning will commence when funds are available

9

Drakenstein Medium B*

Zinc construction

Planning will commence when funds are available

10

Pollsmoor Medium B*

Zinc construction

Planning will commence when funds are available

11

Groenpunt Medium*

Zinc construction

Planning will commence when funds are available

12

Brandvlei Medium*

Zinc construction

Planning will commence when funds are available

13

Brandvlei Maximum*

Closed

Closed. Repair and renovation project is in planning stage

14

Umzimkhulu*

Closed

Closed. Repair and renovation project is in planning stage

15

Geluk*

Closed

Closed. Planning will commence when funds are available

16

Standerton

Completed 2019/20

Upgrading and addition of 787 bed spaces, completed during 2019/20

17

Estcourt

Completed 2019/20

Upgrading and addition of 309 bed spaces, completed during 2019/20

18

Parys

Under construction

Upgrading and addition of 176 bed spaces commenced in 2019

19

Burgersdorp

Planning

Planning for an upgrading project to create 311 additional bed spaces is at an advanced stage; construction to commence in 2020/2021

20

Bethal

Planning

Planning is underway for a major repair and renovation project under the DPWI “Planned Maintenance” budget

21

Mahikeng

Planning

Planning is underway for a major repair and renovation project under the DPWI “Planned Maintenance” budget

22

Port Shepstone

Planning

Planning is underway for a major repair and renovation project under the DPWI “Planned Maintenance” budget

Source file