Question NW1293 to the Minister of Trade and Industry

Share this page:

18 November 2019 - NW1293

Profile picture: Roos, Mr AC

Roos, Mr AC to ask the Minister of Trade and Industry

With reference to his reply to question 802 on 14 October 2019, wherein he indicated that the first phase of the Ekandustria Revitalisation Programme was completed on 27 March 2019, what (a) are the deliverables for the second phase of the programme, (b) is the progress of the second phase as at the latest specified date for which information is available, (c) is the envisaged completion date of the second phase and (d) amount has been budgeted or allocated to the second phase in the 2019-20 financial year? NW2504E

Reply:

The revitalization of Ekandustria Industrial Park for Phase 2 has been scoped and the application has been submitted for funding but not yet processed. I am advised that part of the scope includes the following:

  1. Refurbishment of fire hydrants
  2. Refurbishment of Buildings and roofs
  3. Solid Landfill refurbishment and compliance
  4. Storm water refurbishment
  5. Electrical Reticulations and refurbishment of high mast lights
  6. Construction of Pre -Treatment Plant
  7. Completion of fencing.

b) The second phase has not been initiated as yet pending funding approval.

c) The completion date will be determined following the initiation of the project.

d) The budgeted allocation for the second phase is dependant on budgetary approval.