Question NW764 to the Minister of Human Settlements, Water and Sanitation

Share this page:

13 September 2019 - NW764

Profile picture: Basson, Ms J

Basson, Ms J to ask the Minister of Human Settlements, Water and Sanitation

(a) By what date will the second phase of the Lesotho Highlands Water Project be completed and (b) what is the projected final cost?

Reply:

a) Impoundment of water in Polihali Dam will commence in mid Aug 2024 and water deliveries to Katse Dam in Feb 2026. The planned date of completion of the Project is measured when the first water can be delivered from Polihali Dam into Katse Dam.

PHASE II

MASTER IMPLEMENTATION PROGRAM

ITEMS

CRITICAL DATES

Designs of Advanced Infrastructure commenced

Apr 2015 – end Sept 2018

Award tenders for construction of Advanced Infrastructure

End June 2018 – Jan 2020

Tenders awarded for Polihali Dam design and Polihali Tunnel design

Dam: Jul 2017

Tunnel: Nov 2017

Award tenders for construction of Polihali Dam and Tunnel

Dam: Sept 2020

Tunnel: Apr 2020

Start impounding water in Polihali dam

Aug 2024

Water delivery to augment Katse Dam for RSA deliveries

Feb2026 (Highly dependent on reasonable rainfall)

(b) The final cost at completion of Phase II of the Project in 2026 will be R 32,562,290,145.00 this includes provision for escalation due to inflation up to 2026, and a contingency amount to take care of unforeseen circumstances during the implementation of all features of the Project.

PHASE II

BUDGET AND EXPENDITURE TO DATE

Water Transfer : Audited costs to June 2019

Cost by Category

Revised LTCP

(Nov 2018)

Cost to Date

(June 2019)

Expended %

All Engineering

2,100,100,033

350 897 766

16,7%

Construction - Main works

13,204,085,486

-

0,0%

Construction - Advanced infrastructure

4,800,345,677

114 284 833

2,4%

Administration & PMU

551,542,109

325 681 635

59,0%

Environmental & Social

1,201,963,757

105 330 757

8,8%

Sub-totals

21,858,037,062

896 194 991

4,1%

Escalation – LSL (Lesotho Loti)

4,432,007,238

75 305 037

1,7%

Escalation – Forex

2,989,867,884

48 158 208

1,6%

Sub-totals

29,279,912,184

1 019 658 236

3,5%

Contingency

3,282,377,961

67 556 115

2,1%

Total

32,562,290,145

1 087 214 351

3,3%

Note:

1. “Cost to date” will increase rapidly since a large number of construction contracts were awarded lately.

2. LTCP = Long Term Cost Plan

Source file