Question NW2296 to the Minister of Health

Share this page:

08 October 2018 - NW2296

Profile picture: Dreyer, Ms AM

Dreyer, Ms AM to ask the Minister of Health

(1)What (a)(i) was the original costing and (ii) is the current costing of demolishing the Kempton Park Hospital and (b) are the reasons for the huge difference in the costing; (2) given the new costing, will his department consider refurbishing the hospital rather than demolishing it; if not, why not?

Reply:

1. (a) (i) R127, 729, 665. 36

(ii) R127, 729, 665.36

(b) There is no difference in the demolition cost.

2. Yes, this is one of the of the options under consideration

END.

Source file