Question NW2487 to the Minister of Transport

Share this page:

20 September 2018 - NW2487

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Transport

With reference to the reply to question 673 on 23 April 2018 regarding already built infrastructure to date, (a) what infrastructure has already been built, (b) by what date was each completed in each instance, (c) what were the set completion dates against planned dates, (d) what monitoring mechanisms took place in each instance and (e) what (i) did each monitoring report indicate in respect of each location and (ii) were the deficiencies identified?

Reply:

(a) what infrastructure has already been built, (b) by what date was each completed in each instance, (c) what were the set completion dates against planned dates, (d) what monitoring mechanisms took place in each instance and (e) what (i) did each monitoring report indicate in respect of each location and (ii) were the deficiencies identified?

Plans/

Programme

Region

a)

Key Milestones

c)

Projected Completion Date

b)

Completion date

d)

Monitoring Mechanism Applied

e) i)

Results of monitoring report

e) ii)

Deficiencies identified

Re-Signalling Programme

KwaZulu/Natal (KZN)

 

07 Dec 2021

       
   

Phase 1: Pinetown line

Phase 1B - 15 Sept 2018

Phase 1A – 17 Dec 2017

Project Progress meetings;

December 2017 - commissioned

 
 

Western Cape (WC)

 

30 Jan 2020

       
   

Phase 1.2: Wynberg – Simonstown, Crawford – Diep River

30 Apr 2018

30 Apr 2018

Project Progress Meeting; Monthly report;

April 2018 commissioned except Simonstown that is delayed to Sep 2018

Theft and Vandalism is largely destabilizing the implementation

   

Phase 1.3: Salt River - Kenilworth

18 Mar 2018

2 Jul 2018

Project Progress Meeting; Monthly report;

July 2018 commissioned

Illegal encroachment into the Rail reserve. Security challenges prohibited to work on the central lines.

 

Gauteng

 

28 Feb 2021

       
   

Gauteng Nerve Centre (GNC)

22 May 2015

30 Nov 2015

Project Progress meetings;

Commissioned

 
   

Phase 1: Midway – Residentia

15 May 2015

31 Mar 2016

Project Progress Meeting; Monthly report

Commissioned

 
   

Phase 2: Kaalfontein – Leralla, Olifantsfontein – Irene

03 Dec 2015

28 Nov 2016

Project Progress meetings;

Commissioned

 
   

Phase 3: Randfontein – Roodepoort

05 Mar 2016

15 May 2017

Project Progress Meeting; Monthly report

Commissioned

 
   

Phase 4: Boksburg East – Springs, Daveyton – Alliance

11 May 2016

15 Dec 2017

Project Progress Meeting; Monthly report

Commissioned

 
   

Phase 5: George Goch – Geldenhuys, Benrose – Kaserne West, Booysens – Crown

3 Apr 2018

26 Jan 2018

Project Progress Meeting; Monthly report

BOY – CRN:

09 Dec 2018

Remainder January 2018 commissioned

 

Depot Modernisation

Wolmerton

Gauteng North

Phase 1 complete

Phase 2 in testing & commissioning scheduled for completion by end March 2018

31 Mar 2018

30 Jun 2018

Project Progress Meeting

Practical Completion certificate issued

Holistic planning for depot cannot be achieved if done in parts. Holistic plan for entire depot’s services will be done in Phase 3 Turnkey project.

Source file