Department of Correctional Services 2007/08 Budget and Strategic Plan: briefing
NCOP Security and Justice
28 March 2007
Meeting Summary
A summary of this committee meeting is not yet available.
Meeting report
SECURITY AND CONSTITUTIONAL AFFAIRS SELECT COMMITTEE
28 March 2007
DEPARTMENT OF CORRECTIONAL SERVICES 2007/08 BUDGET AND STRATEGIC PLAN:
BRIEFING
Chairperson: Kgoshi L Mokoena (ANC)
Documents handed out:
Department of
Correctional Services Strategic Plan 2007/8-2011/12 Presentation
Department of Correctional Services Strategic Plan 2007/8-2011/12 [available
later on www.dcs.gov.za]
Presentation by
the Department of Correctional Services, 2007 Estimates of National Expenditure
Audio
Recording of the Meeting (Part 1) and (Part 2)
SUMMARY
The Department presented the strategic plan for the coming year as well as
the Estimates of the National Expenditure. The background to the strategic plan
included an evaluation of strategic planning and performance by the Executive
Management Committee, which discovered that there was a need to have a phased
approach to priorities, as some would take longer than a year. There was a need
to focus on enhancing the role of operational management in the DCS for better
delivery and on creating enabling conditions for delivery on the White Paper. A
five-year plan prioritised the first year of operation. An integrated planning
approach was created. Highlights of
2006/07 included improvement in security with the implementation and rollout of
Biometric systems and monitoring of security policy. There was re-launch and
finalisation of the HIV/Syphilis prevalence survey. Posts at the senior
management level were filled. Sites were accredited for the provision of Anti-Retroviral treatment (ARVs) The move toward a
seven-day establishment and accelerated recruitment for additional staff
continued. The Corrections Week was launched and the Jali
Commission Report was released. Key projects for the next two years included
expediting new correctional centres and improvements to physical
infrastructure. The phased implementation of the Offender Rehabilitation Path
(ORP) and of the Social Reintegration Action plan, and Management of Awaiting Trial
Detention Project and the Job Refinement and Enhancement Project were included.
The programmes were cross cutting. The critical strategies of programmes were
outlined. The processing of the Correctional Service Amendment Bill would be
finalised. There was a review and improvement of measures to ensure safety and
security of inmates, officials and service providers. Installation of security
equipment would be completed at 25% of correctional centres. There would be
reduced overcrowding and removal of awaiting-trial prisoners and sentenced
children from correctional centres to appropriate facilities. Healthcare and
agricultural programmes would be improved. The challenges included the system
of provision of three meals to offenders, the job refinement and enhancement
project, increased participation of offenders in rehabilitation programmes,
escapes involving collusion and violence, attracting and retaining scarce
skills, the finalisation and implementation of policies and procedures,
improved delivery at management area level, taking into account local
government’s role and the alignment of the planning, budgeting and reporting
framework.
The budget was fully outlined, with an indication of the cost drivers used.
Inflation was provided for at 5%. The key cost drivers were personnel totals,
numbers of inmates, including those awaiting trial, probationer and parolees as
well as strategic intentions. Staffing budgets were Head Office at R32, 3
million; Major Prisons at R73, 4 million and second White Paper posts at R57
million. The current inmate population figures were 152 548. The baseline
allocation was R10.7 billion for 2007/08 and a breakdown was given across all
programmes. This represented a 9.26% increase on the previous year.
A number of questions were asked. The
Chairperson noted that the Department could respond to some questions in
writing and deal with other issues at the forthcoming workshop. Questions
included construction of the new facilities, the programme around the White
Paper, the surrendering of R800 million back to National Treasury, the costs of
providing accommodation to prisoners, social reintegration, the human resources
strategies, including salaries, the issue of clustering, use of consultants,
and lessons from the rest of Africa. Other issues concerned awaiting trial
detainees, the costs of inmates, the salaries and costings used by National
Treasury, the security in larger and smaller centres, and the training
programmes. The cluster issue was raised. Other issues that were raised were
put aside to be dealt with when a workshop took place between the DCS and the
committee and time would not permit all the questions to be answered.
MINUTES
Introductory Remarks
The Chairperson noted that the Department of Correctional Services (DCS)
had been honest with regard to their budget, which was appreciated. The
Committee wished to know the progress had on the four additional correctional
facilities that were being built. The successes and frustrations needed to be
shared with the Committee so that help could be given.
Department of Correctional Services (DCS) Strategic Plan 2007/8 to 2011/12
Ms Jennifer Schreiner, Chief Deputy Commissioner: Operations and Management
Support, DCS, briefed the Committee. The background to the strategic plan included
an evaluation of strategic planning and performance by the Executive Management
Committee (EMC), which discovered that there was a need to have a phased
approach to priorities, as some would take longer than a year. There was a need
to focus on enhancing the role of operational management in the DCS for better
delivery and on creating enabling conditions for delivery on the White Paper. A
five-year plan prioritised the first year of operation. DCS formulated revised
targets for the first year. An integrated planning approach was created, which
included an extended EMC work session, dealt with Cabinet Lekgotla
and State of the Nation Address priories as well as a government programme of
action.
The highlights of 2006/07 included improvement in security with the
implementation and rollout of Biometric systems and monitoring of security
policy. There was re-launch and finalisation of the HIV/Syphilis prevalence
survey. Posts at the senior management level were filled. Sites were accredited
for the provision of Anti-Retroviral treatment (ARVs)
The move toward a seven-day establishment and accelerated recruitment for
additional staff continued. The Corrections Week was launched and the Jali Commission Report was released.
The key projects for 2007 to 2009 included expediting procurement of the new
correctional centres and the necessary improvements to physical infrastructure.
The phased implementation of the Offender Rehabilitation Path (ORP) and of the
Social Reintegration action plan, and Management of Awaiting Trial Detention
Project and the Job Refinement and Enhancement Project were included.
Priorities for 2007/08 were improved planning, the creation of an enabling
environment for rehabilitation, improvements in compliance with Internal
Control and Policies, implementation and reporting framework, improved
communication of DCS’ Strategic Direction, implementation of the integrated
human resources strategy and the improvement of partnerships and external
relations.
It was noted that the programmes were cross cutting. The critical strategies
were outlined in these projects. Compliance improvement plans involved managers
with internal controls and procedures at both operational and support levels.
Improved compliance in relation to the Chapter Nine institutions and other
statutory bodies, as well as with the Public Finance Management Act (PFMA) and
internal financial management controls were prioritised. The processing of the
Correctional Service Amendment Bill would be finalised.
There was a review and improvement of measures to ensure safety and security of
inmates, officials and service providers, which would in turn reduce incidents
of escapes and assaults by 10%. Unnatural deaths would be reduced by 5%. The installation of security equipment would
be completed at 25% of correctional centres. There would be a reduced and even
spreading of overcrowding of sentenced offenders as well as a facilitated
removal of awaiting-trial prisoners and sentenced children from correctional
centres to appropriate facilities. Implementation of a comprehensive health
care service would take place with a review of the current system and
development of the new programmes. The maintenance and expansion of a national
agricultural and production workshop system would work in favour of poverty
alleviation.
The challenges faced by the DCS included the system of provision of three meals
to offenders, the job refinement and enhancement project, increased
participation of offenders in rehabilitation programmes, escapes involving collusion
and violence, attracting and retaining scarce skills, the finalisation and
implementation of policies and procedures, improved delivery at management area
level, taking into account local government’s role and the alignment of the
planning, budgeting and reporting framework.
Ms Schreiner concluded that DCS had built on the EMC evaluation and stressed
that it had to be more strategically focused in order to create enabling
conditions for delivery on the White Paper. DCS had also ensured that all key
projects were reflected in the Strategic Plan.
DCS Budget Briefing
Ms Nandi Mareka, Deputy
Commissioner Financial and Management Accounting, DCS, explained the principles
of calculating allocations from a zero base as well as an incremental base as
prescribed by the Medium-term Expenditure Framework (MTEF) manual. The zero
base dealt mainly with non-recurrent expenditure such as capital projects. The
incremental base consisted of historical data taken into account during the
budgeting phase as well as cost drivers and offender totals. Inflation was
provided for at 5%. The key cost drivers were personnel totals, numbers of
inmates, including those awaiting trial, probationer and parolees as well as
strategic intentions.
Ms Mareka explained that employee statistics were 464 posts for the major five
correctional centres (Grootvlei,
Johannesburg, Pretoria, Pollsmoor, Westville),
300 White Paper posts and 118 Head Office posts. The budgets for these were, respectively, Head Office at R32, 3
million; Major Prisons at R73, 4 million and second White Paper posts at R57
million. Allocation of basic salary was based on salary notches and the annual
salary adjustment according to allowances. A three-year phase of having Seven
Day Establishments had begun to be implemented. The medical aid provision for
pensioners was budgeted at R1521 each, while serving members were budgeted at
R1014. Provision made for overtime was made in accordance with the rules set by
the Basic Conditions of Employment Act. Capital Remuneration, Employment
Control Bargain Council, Leave Discounting and Periodic Payment were all based
on the per capita cost.
The provision for interim promotion was captured on the Estimates of National
Expenditure (ENE). Goods and services were costed from indirect expenditure
over the new services and these would be based on the new prices and tariffs
quotations. Property management was devolved from the Department of Public
Works (DPW) to departments. The amount that the staff paid for rent of
accommodation would be recovered from the DCS.
The buildings and other fixed structures would be based on cost and space
norms. Indigent gratuity given to prisoners upon release was based on new
tariffs and the possible projected number that would qualify. The Machinery equipment
minimum allocation was R5000 and the principles were all subjected to the
availability of the budget.
The current inmate population figures were based on Management Information
System of the inmates. The budget had not been taken away from the National
Treasury. The current inmate population was 152 548. The ENE Baseline
allocations projections showed an increase. The compensation of employees
amounts were reinstated over three years and a vacancy rate of 5% to be
decreased to 3% in line with the reduced budget. Health Care professionals’
remuneration would be increased to encourage Health Care professionals to
remain and return to the system. The baseline allocation was R10.7 billion for
2007/08 and a breakdown was given across all programmes. This represented a
9.26% increase on the previous year.
Discussion
A number of questions were asked. The Chairperson noted that more than
twenty questions were asked at the outset, so that the Department would only be
able to respond to some. Others could be responded to in writing. During the
forthcoming workshop with the Department the other issues raised could be dealt
with, which might also include some issues outside the presentations.
Dr van Heerden (DA) stated that the Ministry must be present at some point in
the workshop and that this needed to take place before the debates.
Ms Schreiner noted that the plans of human resources and corporate finance
could also be dealt with in the two-day workshop with the committee.
Mr S Shiceka (ANC)(Gauteng) stated that the budget went beyond the regions and
the allocations of resources. The construction of the new facilities and the
programme of the department around the White Paper were questioned.
Ms Schreiner said that at National and Regional level a good understanding of
the direction of DCS is needed. This had not been satisfactory achieved yet and
workshops were held in all regions to deal with that, in the same way that the
White Paper was workshopped to regional levels. The level of integration needed
to be tested.
The Chairperson and Mr Shiceka asked for motivation of the surrendering of R800
million and return of R167 million for capital projects needed to be motivated
and reasons given why the full allocation was not spent.
Mr Vernon Peterson, Regional Commissioner, Gauteng, answered on the
surrendering of the funds by the DCS. He recalled that in the past there had
been overspending over many years because of the overtime budget and the
medical aid, which was greater than required. The phasing out of Saturday as an
abnormal workday helped to save money. The total saved was roughly R760
million. The saving of the money over time created room for 8311 positions to
be filled. The R800 million now referred to could not be spent in a two or even
five-year period. The understanding of National Treasury, when taking back
those funds that could not be spent, was that the surrendered money was to be
scheduled for re-release when the Department showed the ability to spend it.
The success in the budgeting had been that the Department had saved money and
created and filled new jobs. This was on target with the strategies. The
surrendered funds included amounts for the appointment of staff for the new
correctional centres that had not yet been built yet, and this amount would be
given back once the facilities had been built.
The cost of providing accommodation to the offenders was queried.
Mr Worth also enquired as to the cost driver for the offender population and
why the figures were only going up by 1000 per financial year. The probation
numbers were also increasing by a set margin, and he asked did this also
include the awaiting trial population.
Ms N Mareka commented that the cost per day of offenders included R153.73 per
day for inmates. Excluding the Capital Works Programme (CWP) the cost would be R139.33 per day. The CWP
included the construction of the facilities. Supervision cases came to R13.44
per day.
The Regional allocations would be provided in writing.
Mr Shiceka asked why the Department of Public Works had been mentioned in the
budget. He asked at what point would the distinction be made between the
responsibilities of Public Works and that of the DCS.
Mr Shiceka noted that with regard to the White Paper the DCS was maturing and
sharing views in policy development. Middle management needed to share the same
views in transformation and so he asked what measures would be taken to
encourage the management to act in the same way. The programme for
transformation needed to empower the staff to be able to take decisions. He
concluded that the plan was taking shape.
Mr Shiceka asked if the mobilisation of the DCS included the communities around
the direction of the DCS and if it was communicated properly.
Ms Schreiner said that on social re-integration, a full report needed to be
presented to the house, including the progress. This answer also referred to
the later question posed on the involvement of other community organisations.
Mr Moseki (ANC) commended the DCS on a good presentation and said that the
basics were in place. He expressed concern on the HR aspects of the strategy.
He mentioned that the clustering of DCS with the Security Cluster needed
consideration. Skills were identified but development must be taken into
account and middle management vacancies be filled.
Mr Alfred Tsetsane, Chief Deputy Commissioner, Corporate Services, DCS, said
that the issue of clustering needed support from a political level. There was a
General Public Service Bargaining Council which would assist Correctional
Services into the Security Cluster but there seemed to be blockage at the
higher levels with regard to this.
Mr Ntuli (ANC) questioned what the time frames were as to the goals set so that
the Committee could monitor and play an active oversight role.
Ms Schreiner noted that the Corporate Services and human development had
undertaken training and a full report would be issued. It was agreed that the
work session should be scheduled at a sooner date.
Mr Ntuli asked about alignment with the new demarcations and what measurement
tool was used for rehabilitation. He also asked how restorative justice was
implemented in the DCS and what programmes on rehabilitation of offenders into
their communities were currently running.
Mr Ntuli asked about the psychological reasons for violent crime.
Ms Schreiner noted that the psychologists’ role in assessment should inform the
profile report of each individual offender and a sentence plan was outlined for
the interventions for that offender that were needed for the duration of the
sentence.
Mr W Le Roux (DA) queried why the building of facilities was not taking place
and commented on the lack of space in the current facilities. In the budget
there was provision for new office space even though the buildings to house the
inmates had not yet been completed, and he questioned why there was this
discrepancy. He also noted that the budget reflected spending of 60% more on
well being of inmates and 30% more on the compensation of staff, but the
consultancy fee had increased by 300%.
Ms Mareka noted that there should be a separate presentation on facilities as
this could properly be explained then.
Dr van Heerden (DA) commented that Ms Schreiner stated that it was proposed to
have a Seven-day establishment running, and he queried if the recruitment of
staff reflected that. He also asked if in attracting and retaining scarce
skills, skills that had left or were no longer in service were included.
Ms Schreiner stated that In trying to attract people DCS would look at trying
to bring back scarce skills and other frameworks were being developed in head
hunting. This would include different procedures.
The Chairperson commented that the challenges to the DCS were the alarming
vacancy rates and the fact that the posts that were filled in the 2005/06 year
were less than the vacancies available. The Auditor General had also enquired
as to why all vacancies were not filled. DCS had the finance to do so and the
filling of posts was key to the security of the prisons.
Mr Alfred Tsetsane, Chief Deputy Commissioner, Corporate Services, DCS, stated
that the vacancy levels in the correctional services were standing at 7% and
the fears around vacancies related to scarce skills that were critical to the
core business. These professionals were scarce countrywide. A strategy was
being developed to attract and retain these skills in the DCS in a Scarce
Skills Strategy. Statistics were issued quarterly on vacancies in the
Department. The perception that the necessary numbers were not being recruited
was incorrect although the ratios between offenders and staff could be
improved. Another dynamic was the extent to which staff were “recycled”,
including promotions. The trends of the turnaround time may have to be
followed. In filling the posts in correctional centres it was not easy to draw
personnel from outside the institution.
Mr Tsetsane also said that consultants were used for recruitment, good
benefits, detection of corrupt activities and the managing of risk around
officials. The consultancies would issue a report at the end of the year. The
performance of the companies would be looked at and other strategies
considered.
Dr van Heerden said that it would be helpful to learn from Northern Africa, and
the ex-French territories, to expand the vision of DCS.
DCS responded that the building of an All Africa Correction Structure was in
the process to make sure that in Africa best practises could be shared. DCS had
been concentrating on the Southeast and Central Africa and was about to expand
through the All Africa Correctional Body.
Dr van Heerden asked how would the promotion of alternative sentencing be
promoted through Department of Justice, and queried if this would not have to
go to the South African Law Reform Commission.
Ms Schreiner said that there was a challenge in that the judiciary had no
confidence in the Community Corrections System and sometimes also in utilising
the Criminal Procedure Act. DCS was interacting with the magistrates in order
to explain how the community correction system worked and what direction the
streamlining of the community correction system was taking. It was necessary to
instil confidence in the judiciary about the community correction system and to
stress that it was an option that worked, not just a parole option.
Mr D Worth (DA, Free State) commented on the staff shortages and questioned why
outsourcing was used to recruit staff and why overtime for the staff was going
to be stopped now, even if it was going to be phased back in at a later date.
Ms F Nyanda (ANC, Mpumulanga) asked if the facilities planning included the
upgrading of existing facilities and how many renovations were envisaged.
Ms Nyanda asked whether in operation of outreach to the communities church
groups, NGO’s and local structures were included and if this was not so, the
reasons for this.
Ms Nyanda noted that security equipment was installed at 25% of correctional
centres at a cost of R73,4 million, and she enquired as to why the small
centres were not included in this amount.
Ms Mareka indicated that providing the funding for the recruitment for big five
centres did not disregarded the small centres, as the DCS had taken an informed
decision to enhance the capacity of those centres. The other R60 million that
was available in the 2006/7 financial year was for implementation of white paper
for all centres, and enhancement of security measures and better management of
the centres. This was not at the expense of the small centres. The basis of the
cost driver would come in writing to the committee.
Ms N Mareka stated that a reply to all facilities questions needed a full
presentation by relevant role players.
Ms Nyanda asked where children awaiting trial were kept.
Mr L Fielding (DA, Northern Cape) asked what relationship DCS had with the DPW.
He also enquired as to the relationship between DCS and the local government,
especially with reference to social problems.
Mr N Mack (ANC, Western Cape) commented that the DCS was trying to improve. He
said, however, that the recruitment figures for staff were static and the ratio
of 30 inmates to one official made for great stress on the officials. The more
dangerous inmates needed more surveillance and the ratios needed to be aligned
for establishments. When the budget was drawn up again it needed to be more
structured to reflect the needs of the establishment. More staff needed to be
recruited to top and middle management.
Mr Mack asked why the targets for risk assessment and profiling of 23% were not
met and if this would begin again in 2007. The cost of tracking down of
absconders was questioned.
Mr Mack noted that there appeared to be a problem with the communications
between the transport of prisoners to court and the holding cell officials, as
many inmates did not always arrive for trial, and he asked what the cost of
this was.
The Chairperson asked about the hunger strike by inmates in Pretoria, as it was
thought that this happened because the wrong people were given parole. The
monitoring of those on parole by the parole boards was necessary and could be
done if the boards were doing what was expected of them.
A DCS official stated that the ten parole seekers considered that they had been
incorrectly dealt with under the 1959 Act and instigated others on the hunger
strike in the same facility. The Regional Commissioner went there in person to
address the inmates, as had the Chairperson of the Parole Board. It was agreed
that the Regional Commissioner would form a small task team that would look at
the inmates’ specific cases and would also address their parole board issues.
The Regional Commissioner also visited Rooigrond and Rustenburg the following
week to address offenders on the same issues. This issue needed to be addressed
by the DCS as there was no understanding from offenders with regard to parole.
Two offenders might have committed the same offence, yet their participation
and their behaviour in the institutions and their reports for parole purposes
would be different.
It was noted that there was now a new Parole Board that had been through
training to ensure the adequate supervision in the centres. The reports come
through the Case Management Committee, which was trained in these issues. It
was ensured that any reports that were processed were correct, including those
of the psychologist and social worker in the section. The Case Management
Committee must receive correct reports. Recommendations would assist the Chair
of the Parole Board, but the final decision rested with the centre so its
correctness could be assessed. The outcome of the investigation team was
awaited. The Regional Commissioner agreed upon a time frame.
The Chairperson commented that the
shortcomings of DCS included the fact that the monthly statements were not
submitted on time. Salaries were not paid on time and the certificates were not
filled in annually which made it difficult to audit the DCS. The priorities of
the DCS were questioned and also how it would ensure that the trip sheets would
be maintained and that documents would be submitted to the Auditor General so
that reports could be compiled. It was noted that logbooks and trip sheets did
not correspond and were not being filled in correctly and this was not
acceptable.
Ms Mareka responded that a steering committee had met and an action plan was
discussed in relation to issues raised by the Auditor General. This plan needed
to be presented to the Committee and it would answer the questions asked by the
Chairperson. Supervision was also an issue and needed a full presentation to
give it justice.
The Chairperson commented that offenders that committed greater and lesser
crimes were being categorised into the same cells. He asked if this also meant
that the rehabilitative programmes for all offenders were the same. He stated
that indirectly criminals would be taught by each other, and could thus move on
to commit harsher crimes.
The awaiting trial detainees and their classifications included the
Correctional Services, South African Police Service and the Home Affairs
Office. There was no distinction as to the crimes as yet as it took time for
the verification to come through.
Ms Schreiner said that the information flow from Department to Department, to
be able to manage the security risks of the Awaiting Trial Detainees, needed to
be improved. A dedicated remand system needed to be established as there was a
difference between those in detention and those in correctional remand.
Assistance was needed in this issue. The non-custodial sentences were not
always utilising the community correction system that was in place.
The Chairperson felt that more needed to be done about the salaries for
officials.
Mr V Petersen said that National Treasury used per capita cost in their
budgets, so the personnel budget divided by the staff numbers would indicate
the amount it would cost the DCS to appoint one person. Increase in salaries
for the DCS from Treasury would be quite slim. The other factors could be
discussed at the upcoming workshop.
Ms Mareka stated that other questions would be addressed in the workshop and
thanked the committee for the oversight role and for engaging with the DCS.
The meeting was adjourned.
Audio
No related
Documents
No related documents
Present
- We don't have attendance info for this committee meeting
Download as PDF
You can download this page as a PDF using your browser's print functionality. Click on the "Print" button below and select the "PDF" option under destinations/printers.
See detailed instructions for your browser here.