Roads and Transport Provincial Departments First Quarter Conditional Grant 2006/07: hearings
NCOP Finance
13 September 2006
Meeting Summary
A summary of this committee meeting is not yet available.
Meeting report
FINANCE SELECT COMMITTEE
13 SEPTEMBER 2006
ROADS AND TRANSPORT PROVINCIAL DEPARTMENTS FIRST QUARTER CONDITIONAL GRANT
2006/07: HEARINGS
Chairperson: Mr T Ralane (ANC) (Free State)
Documents handed out:
Kwa-Zulu Natal Department
of Roads and Transport presentation
Gauteng Department
of Roads and Transport presentation
Western Province Department of Roads and Transport presentation
Limpopo
Department of Roads and Transport presentation
Eastern Cape Department
of Roads and Transport presentation
Free State
Department of Roads and Transport presentation
SUMMARY
Kwa-Zulu Natal said that they had spent 25% of their budget in the first
quarter, and were actually going to slow down spending to remove the risk of
overspending. The Department needed a further allocation of R18 billion over
the next five years. They had enough capacity and evaluation systems in place
to deliver on their mandate.
The Western Province said that their capital expenditure for roads
infrastructure for the first quarter amounted to R114 298 million or 12.6% of
their budget. There was a slow start to spending in the quarter on the
conditional grant. In terms of their capacity to spend, skills in engineering
and quantity surveying were in short supply and posts were hard to fill.
The Eastern Cape said that they had been allocated R742 057 million and had
spent R175 910 million (24%) by the 30 June 2006. Reasons for the variances were that
some of the projects are starting in September 2006. Challenges included prevailing
provincial conditions such as backlogs and climatic and geological problems.
The Free State said that on roads, they had spent R12.2 million in April which
was a bit low, R39 million in May and R43 million in June. This amounted to
under-expenditure of R52 million over this period. This was caused by the
re-planning in March and April necessitated by the heavy rains that affected
the Province. Some of the challenges the Department faced were that planning
procedures were still not where they should be and there were still problems in
project management including monitoring. There were still challenges created by
the backlogs caused by the floods and there were problems in attracting more
skills.
Gauteng said that in capital expenditure, R69 658 000 (16%) had been spent of
the R432 554 000 budget which was a bit low due to disruptions caused by heavy
rains. Projections were however, that the full allocation was going to be
spent. The delay in the
sign-off of the financial implications of the Gautrain project may lead to
under-expenditure. Indications were that the financial closure would be reached
towards the end of September 2006 and this milestone would accelerate
expenditure.
Limpopo said that of a R1 100 888 000 budget, R156 676 000 (14.23%) had been
spent. The Road Agency
Limpopo submitted monthly, quarterly and annual reports to the Department and
the Provincial Treasury.
MINUTES
Kwa-Zulu Natal Department of Roads and Transport Presentation on 1st
Quarter Conditional Grants.
Dr K Mbanjwa, Head of Department (HOD), said that their allocation for
infrastructure was R1.825 billion, with R1.477 billion came from their own
fiscus with the remaining 348 million coming from the Provincial Infrastructure
Grant (PIG). They had spent 25% of their budget in the first quarter, and were
actually going to slow down spending to remove the risk of overspending. In
terms of some outputs, they had committed to build 59 gravel roads in the
Empangeni Region and had so far completed eight. In the Ladysmith area, they
had spent R10.5 million.
The Department needed a further allocation of R18 billion over the next five
years. They had enough capacity and evaluation systems in place to deliver on
their mandate. Massification of their rural growth and development was not
possible unless supported by appropriate transport infrastructure.
Discussion
The Chairperson said that he was worried that they had only spent 17%
of their equitable share. Dr Mbanjwa had claimed that they had spent 25% of
their budget but the Treasury report said that they had only spent 19.3%. Why
did they not first use their equitable share budget and then use the PIG?
Provincial Treasuries were erring in making PIG available too easily. It should
only be disbursed on the basis of Departments’ capacity to spend. Since they
had only spent 17% of their equitable share it was clear that they did not have
that capacity. They were failing to spend R1.4 billion and yet they wanted R18
billion more.
Mr E Sogoni (ANC) (Gauteng) said that Provinces were rushing to spend money but
the important thing now was to ensure that there was quality work being done.
The Chairperson announced that there was new funding for Municipalities for
public transport infrastructure and systems of R519 million for this year and
R624 million for next year from the national Department. It was meant to
accelerate planning and the construction and improvement of new and existing
public transport and systems. It would be very interesting how they were going
to disburse this without duplicating what Provincial Departments were doing.
Western Province Department of Roads and Transport Presentation on 1st
Quarter Conditional Grants
The Acting Head of Department said that their capital expenditure for roads
infrastructure for the first quarter amounted to R114 298 million or 12.6% of
their budget. There was a slow start to spending in the quarter on the
conditional grant (CG) as the cash-flow had adjusted to compensate for
difficulties in accessing certain areas, delays in awarding tenders and delays
in obtaining environmental assessment approvals.
On public transport, R8 million would be transferred to the Department of
Public Works and the construction of an impoundment facility at Beaufort West
would was planned to begin later in the year.
In terms of capital expenditure on agriculture, R3.536 million or 31.43% of the
budget had been spent. The total included a rollover that had been requested of
R4.319 million. Public Works had therefore already spent more than 75% of its
original budget of R2 million in the first quarter.
In terms of the Department’s compliance with the Division of Revenue Act
(DORA), they had submitted detailed infrastructure plans for the 2006 budget by
the 14th of April 2006 for Departments that were targeted by the
grant. The Department was expected to prioritise the rehabilitation of class 2
roads and identified the freight corridors that executed the projects in
accordance with the Extended Public Works Programme (EPWP) tender and design
guidelines.
In terms of their capacity to spend, skills in engineering and quantity
surveying were in short supply and posts were hard to fill. There were
programmes in place to deal with this problem in the long term.
Discussion
The Chairperson reminded the Department that DORA directed that
Departments must not spend more than 1% of their budgets outsourcing external
capacity.
Ms D Robinson (DA) (Western Cape) said that she was really concerned about the
low spending and the lack of capacity in the Province. Did they have any
solutions to these problems?
The Chairperson said the Province had to respond in writing to these concerns.
Eastern Cape Department of Roads and Transport: 1st Quarter
Conditional Grants
MEC T Mhlahlo said that they had been allocated R742 057 million and had
spent R175 910 million (24%) by the 30th of June 2006. Reasons for the variances were that
some of the projects are starting in September 2006 such as Ugie Langeni phase
3, the Middledrift to Alice road and the T15 Mt Frere to Mt Fletcher phase 1.
Also, some projects were being completed in the first quarter.
In managing
and monitoring, Departmental
officials attended monthly site progress meetings. In addition the (Chief
Financial Officer) CFO and programme manager conducted random site visits on
the progress of the contracts. The Department submitted a detailed quarterly
report, which captured the full details of the projects including the
allocation for the year, the expenditure for the period in question and the
outputs achieved.
Specific reports were submitted on progress made with respect to social
indicators such as employment, BEE and local resources. Monthly in-year
Monitoring reports were also submitted to the Provincial Treasury to monitor
the expenditure. The South African National Roads Agency (SANRAL) implemented
three projects on behalf of the Department in terms of a service level
agreement monitored by Departmental staff.
Challenges included prevailing Provincial conditions such as backlogs and
climatic and geological problems. Capital expenditure outweighed the
maintenance allocation (R1.071 billion) where currently, capital expenditure
was 60 % of the total roads budget of R1.795 billion. There was a lack of adequate
funding for roads, and currently only 35% of their maintenance needs were being
met. They also needed to improving internal technical capacity. There was a
long and resource hungry procurement cycle and the quarterly transfers from
National Treasury did not match actual project cash-flows.
Free State Department of Roads and Transport: 1st Quarter
Conditional Grants
MEC S Mohai said that R550 million was allocated to roads infrastructure,
transport was allocated 19.9 million and traffic was allocated R112 million. On
roads, they had spent R12.2 million in April which was a bit low, R39 million
in May and R43 million in June. This amounted to under-expenditure of R52
million over this period. This was caused by the re-planning in March and April
necessitated by the heavy rains that affected the Province. In terms of the new
projections, most of the money for the financial year would be spent by the end
of December and they were engaged with Treasury to obtain extra funds.
In terms of the Department’s capacity to spend, they had built the requisite
capacity within the Department to make sure that they did not outsource the
skills. About 22 posts for engineers were filled at various levels. There was
still a challenge to compensate them appropriately however and this meant that
administration costs were going up.
He admitted that there had not been any expenditure for the EPWP as they had to
implement intervention measures to repair the rain-damaged roads. The
Department also had challenges in dealing with the Departments of Sport, Arts
and Culture and Environmental and Tourism as they had to re-plan. Expenditure
for these Departments was very low.
Some of the challenges the Department faced were that planning procedures were
still not where they should be and there were still problems in project
management including monitoring. There were still challenges created by the
backlogs caused by the floods and there were problems in attracting more
skills. The Taxi Recapitalisation Project had also caused them some problems
as they had to make sure that their testing stations were compliant as they
were critical to the process.
Some of the interventions employed were ensuring that the Department was
appropriately staffed they had changed their planning patterns, had ensured the
fast-tracking of payments to service providers and they were also streamlining
their operations.
Discussion
The Chairperson said that the Department claimed to adequate capacity
to spend but their spending patterns told a different story. Also, their actual
spending out-stripped their cash-flow.
Mr Sogoni said that the picture was not as good as it seemed to be because the
Auditor-General had noted 29 issues that the Department had to deal with. In
one instance R22 million went missing and was unaccounted for.
MEC Mohai replied that the R22 million referred to property management
contracts and really did not affect the Department.
Gauteng Department of Roads and Transport: 1st Quarter
Conditional Grants
Mr D Sedumo, the Chief Financial Officer/Acting Head of Department, said that
the Department had R163 098 million and had spent R34 834 million. In capital
expenditure, R69 658 000 (16%) had been spent of the R432 554 000 budget which
was a bit low due to disruptions caused by heavy rains. Projections were
however, that the full allocation was going to be spent.
Key projects were the
construction of the dual carriageway and two intersections for Cosmo City; the
construction of K60 in Sunninghill; construction of a dual carriageway from
Dalpark to Heidelberg - K109 Old Heidelberg road and the rehabilitation of the
Cullinan road in the Dinokeng area.
He then gave a progress report on the Gautrain. The delay in the sign-off of the financial
implications of the project may lead to under-expenditure. Indications were
that the financial closure would be reached towards the end of September 2006
and this milestone would accelerate expenditure. The budget was R4 641 000 000
of which only R254 405 (5.5%) had been spent.
Mr G
Martins, the Deputy Director-General of Public Works said that in capital works, 16%
(R24 981 080) of the R150 315 000 had been spent. Expenditure in the April was
low due to the commencement of work on site. New projects started this
financial year had a low capital expenditure in the first month. To ensure that
expenditure was maintained at minimum average of R12 million per month in
accordance with the budget allocation, the under-spending in April was being
factored into the proceeding months. Monthly project review meetings were held
to monitor expenditure.
In
maintenance, 32% (R6 434 792) of the R20 million had been spent. Pretoria had the largest number of
Public Works facilities that were required to be maintained; hence the budget
allocation was large in comparison to the other regions. Expenditure is in line
with the projections and monthly project review meeting were held to review
progress and outputs.
Some of their future plans were the introduction of multi-year financial budgeting and implementation for projects and
life cycle
budgeting to be developed at project identification phases. Construction Contact Centres were to be established to assist with contractor development and
project assistance.
In monitoring capacity
and planning, monthly expenditure report meetings were held between programme
managers and the Finance branch. Senior quarterly management meetings were used
to discuss performance of the various programmes and the Executive Management
committee also received monthly expenditure report from the CFO. The HOD and
Deputy Director-General of Public Works held one-on-one meetings with
individual managers from time to time to ensure accountability for service
delivery.
At unit level performance was monitored against operational plans and monthly
and quarterly infrastructure reports were sent to Treasury. Project Management
Resource Groups assisted in ensuring performance happened at site level. Client
Departments needed to have plans developed and implemented.
Limpopo
Department of Roads and Transport: 1st Quarter Conditional Grants
The Chairperson heavily curtailed the presentation and told Dr T Farisani, the
Chief Financial Officer/Acting Head of Department, to focus only on the
Department’s monitoring capacity. In this regard, Dr Farisani said that of a R1
100 888 000 budget, R156 676 000 (14.23%) had been spent.
The Road Agency Limpopo
submitted monthly, quarterly and annual reports to the Department and the
Provincial Treasury. They also submitted any report that may be requested at
anytime to comply with the Department and Provincial Treasury. Service level
agreements were signed after the awarding of tenders to contractors.
Discussion
The Chairperson said that the Limpopo Department still owed the
Committee answers from issues it had raised during their last meeting. They
were still waiting.
Mr Sogoni said that in the future there should be a harmonisation of the
Departments’ reports. The Committee should get the same reports as the National
and Provincial Treasuries.
The meeting was adjourned.
Audio
No related
Documents
No related documents
Present
- We don't have attendance info for this committee meeting
Download as PDF
You can download this page as a PDF using your browser's print functionality. Click on the "Print" button below and select the "PDF" option under destinations/printers.
See detailed instructions for your browser here.